Under the Clean Country federal project, part of the Ecology national project, the Company will remediate the landfill of municipal solid waste 6 km away from Zheleznogorsk. Stage 1 of the landfill remediation project will be technical works, including placing a cover to isolate the landfill with layers of a synthetic geomembrane and natural materials. The cover will divert surface runoff water and reduce leachate, decrease landfill gas emissions, prevent smells and the expansion of the landfill body, and provide ground for plants to root in following the revegetation stage of the project.
Moscow Region, Ruzsky Urban District, near the village of Annino
The Annino landfill operated for 40 years, from 1976 to 2016, accumulating over 900,000 tonnes of waste. A large-scale remediation project began in 2019 and was completed ahead of…
Moscow Region, near Ozherelye Microdistrict, Kashira
Kashirsky landfill, 6.5 km southeast of Kashira, operated between 1974 and December 2015, accumulating 960,000 tonnes of waste.
Remediation of the Bykovo and Kashirsky landfills…
Moscow Region, Dmitrovsky District, Dedenevo urban municipality, near the village of Dyakovo
The Iksha-2 landfill for municipal solid waste is located 8 km away from the Iksha settlement of the Dmitrovsky District in the north of the Moscow Region. The project included…
The project envisaged remediation of the closed Valtsovo landfill for municipal solid waste in the Stupino Urban District.
Closed in 2014, the landfill had accumulated 816,000…
MSU-1 GC acts as the general contractor for projects to remediate municipal solid waste landfills under the Ecology and Environment of the Moscow Region government programme. One…
MSU-1 GC is remediating the Lesnaya landfill in Serpukhov, Moscow Region, as scheduled, planning to complete the project in 2024. The landfill remediation is part of the Clean…